Launch Days 1–2
Day 1
🌊 Flood Relief Kickoff Lab
Launch 45m
Day 2
πŸ“ Bridge Limits Design Brief
Knowledge/Skill Building 45m
Research & Plan Days 3–8
Day 3
🌊 Flood Route Stakeholder Map
Knowledge/Skill Building 45m
Day 4
πŸ“ Bridge Limits and Measures
Knowledge/Skill Building 45m
Day 5
🧱 Bridge Types Evidence Hunt
Research 45m
Day 6
πŸ“ Design Brief Draft
Deliverable 45m
Day 7
πŸ’¬ Design Brief Peer Critique
Project Work 45m
Day 8
βœ… Design Brief Gate Review
Assessment 45m
Decide & Prototype Days 9–13
Day 9
πŸ“Š Weighted Bridge Matrix
Knowledge/Skill Building 40m
Day 10
✏️ Three Bridge Concept Set
Deliverable 45m
Day 11
πŸ—£οΈ Concept Critique Carousel
Project Work 45m
Day 12
βœ… Design Choice Conference
Assessment 40m
Day 13
πŸ› οΈ Rapid Prototype Build
Project Work 45m
Test Revise & Showcase Days 14–18
Day 14
πŸ“ Bridge Test Protocol Rehearsal
Knowledge/Skill Building 35m
πŸ§ͺ Trial 1 Scorecard Run
Project Work 45m
Day 15
πŸ”§ Failure Analysis and Revision Plan
Knowledge/Skill Building 45m
Day 16
πŸ” Trial 2 Retest and Comparison
Project Work 45m
Day 17
Day 18
πŸ—‚οΈ Expo Evidence Board Draft
Deliverable 45m
Showcase Days 19–20
Day 19
πŸ› οΈ Bridge Relief Expo Rehearsal
Deliverable 45m
Day 20
πŸŒ‰ Bridge Relief Expo
Assessment 45m